ARE 5.0 -  Critical Path Method and Gantt Charts

ARE 5.0 - Critical Path Method and Gantt Charts

Hyperfine Architecture

6 лет назад

41,595 Просмотров

Ссылки и html тэги не поддерживаются


Комментарии:

@larrytinnin2818
@larrytinnin2818 - 17.03.2019 21:25

Are you going to re-upload the revit electrical outlet video? It’s not playing

Ответить
@carlosaramburo8183
@carlosaramburo8183 - 19.07.2019 05:44

So I cannot figure out how you got 12 days of float for sheathing-windows-ext.finish. Ive tried and cant figure it out

Ответить
@M5AWD
@M5AWD - 19.09.2019 21:37

I'm not an architect, but this was a perfect explanation of the Critical path / Gantt chart for people not familiar with either. Thanks!

Ответить
@_martzahl9397
@_martzahl9397 - 23.09.2019 06:50

time for a new highlighter

Ответить
@wenyang8552
@wenyang8552 - 01.08.2020 11:35

I felt the "7,8,9" with dash line point toward "10" is the confusing part, "7,8,9" here actually doing nothing but represent "10" , why can't we deleted the three dash lines, and connect "3" to "10" directly with three activities: HVAC, ELECT, PLUMB, by using 3 "curvy lines"? This can reduce confusion and make CPM more straightforward

Ответить
@bennychan8428
@bennychan8428 - 16.03.2022 18:11

Your video is great and very clear , thank you for sharing

Ответить
@ForceMultiplier
@ForceMultiplier - 14.06.2022 20:27

Excellent representation. Thank you!

Ответить
@SA-xj1cs
@SA-xj1cs - 28.08.2022 01:36

Hello, what kind of red marker is that you’re using in the video, where did you purchase it? Thanks!

Ответить
@JulianMAguilar
@JulianMAguilar - 26.01.2023 06:03

Thank you

Ответить
@pabloluislopez3981
@pabloluislopez3981 - 27.01.2023 05:12

I find hyperfine one of the best routes to pass these exams. If you have failed these exams, using hyperfine recaps the content in a nice way with items to do while you answer these questions. But dont expect to pass if you just do hyperfine. Use all the resources you can fine and use hyperfine to recap and refine your knownledge. One of the best investment I have made. Thank you

Ответить
@iabbervocium
@iabbervocium - 25.04.2023 02:57

There's one part I am not understanding, wouldn't you want the roof complete before HVAC & electrical so that it doesn't get rained on?

Ответить
@ArmyLatinoPRO
@ArmyLatinoPRO - 09.06.2023 03:24

IMPECCABLE

Ответить
@sarahmenendez9261
@sarahmenendez9261 - 09.06.2023 17:41

incredibly straight forward and useful. Thanks for this!!

Ответить
@ramirezjakky
@ramirezjakky - 29.05.2024 21:49

thank you for making something like this better to understand!

Ответить
@JulianMAguilar
@JulianMAguilar - 12.07.2024 08:50

ty sir

Ответить
@designconstructionhub
@designconstructionhub - 20.11.2024 07:18

Excellent

Ответить
@dominiccartier9456
@dominiccartier9456 - 15.12.2024 00:19

Shouldn't the "install roofing" portion of the Gantt chart have a start - end relationship with setting the roof trusses? The initial critical path diagram makes it clear that installing the roofing occurs after the trusses have been set, but the Gantt chart has roofing installation happening at the same time you are setting your trusses.

Ответить
@hybridiculous
@hybridiculous - 04.02.2025 23:49

thank you

Ответить
@solomonsteyn8478
@solomonsteyn8478 - 07.03.2025 00:39

So whats the float for exterior finishes based on the gantt chart ?

Ответить
@moctezumacuauhtemoc8470
@moctezumacuauhtemoc8470 - 04.03.2019 22:43

your videos are straight to the point, love them, keep them coming!

Ответить